Peterson construction update Published Aug. 5, 2009 21st Civil Engineer Squadron PETERSON AIR FORCE BASE, Colo. -- The following are ongoing construction projects on Peterson. Base personnel should exercise patience and caution when in the vicinity of these projects. 1. Club canopy construction has an estimated completion date of Aug. 10. The contractor will install light fixtures and landscaping starting the week of Aug. 3. 2. West gate outbound lanes realignment has an ECD of Aug. 15. Crews are currently reworking outside outbound lane. Work began June 29. Outbound traffic is restricted to one lane. Project is stalled due to saturated sub base. A time extension may be required if rain continues. 3. Roundabout construction has a new ECD of mid September. Project was delayed due to wetter than expected conditions.